Main Street Reconstruction

Weekly Updates

3/28/24- Gas Main locating has been complete and the work should begin the week of 4/1/24.

4/4/24- Crews have begun the gas main work with boring beginning on Tuesday 4/9/24

4/9/24- Crews are working on installing the gas line main in the terrace on the north side of Main St.

5/21/24- Gas crews are wrapping up their work this week and should have everyone switched over to the new service. SEWER LINNING WILL BEGIN 5/22 and take about 2 weeks. Please be mindful of water usage. Crews will communicate needs with individual property owners.

Project Timeline

  • Preconstruction Gas Main replacement will begin in April and take about 45 days.
  • Preconstruction Meeting with Koplin and sub contractors took place March 14th at 10:30am
  • Project construction will begin June 3rd
  • Lighting Upgrades will take place during substantial construction phase
  • Construction is tentatively going to wrap up mid September

Project and Parking Map

Newburg Project Map